Shaftwell

The brief

Why now

  • 05/10/2026Won a mining contract on an expansionVelgarrie Mining Services has been awarded a seven year mining services contract for the Larrikoo Well expansion.
  • 04/09/2026Was adding to its mining fleetDelivery of 4 new haul trucks to Larrikoo Well is expected in January.

Who to speak to

Oscar Hendry, Maintenance Manager Decision maker

Suggested first step
They keep maintenance in house. Offer shutdown crews and rebuilds to back their team up. They've won new work, so ask what the fleet and workshop need for it.

Maintenance setup

Own crew

Good to know

  • Latest signal: 05/10/2026
  • Signals on record: 5
  • Sites run under contract: 4
  • Haul trucks: 37
  • Checked by hand: Yes
  • Your customer: No

Signals (5)

Each signal comes from a document, with the sentence behind it. Open one to see it with the people to call.

  1. 05/10/2026Company announcementSets the rank

    Won a mining contract on an expansion

    Velgarrie Mining Services has been awarded a seven year mining services contract for the Larrikoo Well expansion.

    They've won more work on a growing site. Their fleet and workshop will need more support.

    Open the source
  2. 04/09/2026Company announcementSets the rank

    Was adding to its mining fleet

    Delivery of 4 new haul trucks to Larrikoo Well is expected in January.

    New fleet is on the way. It will need workshop space, servicing and electrical work.

    Open the source
  3. 24/10/2025Company announcementSets the rank

    Maintains plant with its own crew

    Fleet maintenance is done by the company's own workshop crews on each site.

    They keep maintenance in house. Shutdowns and rebuilds still need extra hands.

    Open the source

Also on record (2)

Other things the company said, newest first. They didn't set the rank and most haven't been checked by hand.

  1. 11/03/2026Trade press

    Was upgrading its plant

    A new leach circuit is being installed at the Larrikoo Well plant.

    Plant is being upgraded now. Installing, wiring and commissioning it all need extra hands.

    Open the source
  2. 26/12/2025Company announcement

    Scheduled a major plant shutdown

    A 17 day major shutdown of the Larrikoo Well processing plant is scheduled for November.

    A major shutdown needs crews, parts and rebuilds lined up weeks ahead.

    Open the source

People (3)

Who to speak to at Velgarrie Mining Services, decision maker first.

  • Decision maker

    Oscar Hendry

    Maintenance Manager

    Where we found them
    LinkedIn profileChecked 07/10/2026
  • Daily user

    Daniel Kovac

    Maintenance Superintendent

    Email
    Verified
    Where we found them
    LinkedIn profileChecked 05/10/2026
  • Sponsor

    Priya Underhill

    General Manager Operations

    Email
    Verified
    Where we found them
    Company announcementChecked 04/10/2026

Notes (0)

Shared with everyone on your team who has a login. In this demo, what you add stays in your browser and nothing is sent.

    Report a problem with this company

    Tell us if something is wrong or doesn't look right. We check it against the source and fix it in the next update.

    Prepared by Evidential for Shaftwell, a synthetic seller. List of 12/10/2026.