A 49 megawatt hybrid power station is being built at Garrimbee Downs to cut diesel use.

Why it matters

New site power means new switchgear and cabling to install and look after.

Where it comes from

  • Source: Company announcement
  • Document date: 06/07/2026
  • Sets the company's rank: Yes
  • Checked by hand: Yes

Open the source

People to call about it (2)

Who to speak to at Hendravin Mining, decision maker first.

  • Decision maker

    Sofia Tanaka

    Maintenance Manager

    Email
    Verified
    Where we found them
    Company announcementChecked 06/10/2026
  • Daily user

    Arjun Okafor

    Maintenance Superintendent

    Where we found them
    LinkedIn profileChecked 06/10/2026

Notes (0)

Shared with everyone on your team who has a login. In this demo, what you add stays in your browser and nothing is sent.

    Report a problem with this signal

    Tell us if something is wrong or doesn't look right. We check it against the source and fix it in the next update.

    Other signals from Hendravin Mining (5)

    Each one opens the same way.

    1. 02/10/2026Company announcementSets the rank

      Funded a mine expansion

      Funding is in place for the Garrimbee Downs expansion, including a second ball mill and a larger crushing circuit.

      The money for the expansion is in place, so the work is likely to start soon.

      Open the source
    2. 19/08/2026Company announcementSets the rank

      Runs ageing plant or fleet

      The Garrimbee Downs processing plant has been running since 2002.

      The plant or fleet is getting old. Older machines need more repairs and rebuilds.

      Open the source
    3. 07/08/2026Company announcementSets the rank

      Reported lower plant availability

      Plant availability at Garrimbee Downs fell to 79 per cent in the quarter, below the target of 92 per cent.

      Plant availability is below target, so maintenance is under pressure.

      Open the source
    4. 29/07/2026Development approvalSets the rank

      Had a camp extension approved

      Approval has been granted to extend the Garrimbee Downs accommodation village by 211 rooms.

      More rooms on site means more people coming, usually for a build or a shutdown.

      Open the source

    Also on record (1)

    Other things the company said, newest first. They didn't set the rank and most haven't been checked by hand.

    1. 06/03/2026State tenement and mine register

      Applied for a mining lease

      Hendravin Mining applied for a mining lease of 1,246 hectares adjoining Garrimbee Downs.